Main types of planning permission
Contents |
[edit] Introduction
Planning permission is the legal process of determining whether proposed developments should be permitted. Responsibility for planning lies with local planning authorities (usually the planning department of the district or borough council). The legislation, policy and guidance that underpins planning in England can be found on the government's National Planning Practice Guidance website.
Other than permitted developments, (which are considered to have insignificant impact), all developments require planning permission. The Town and Country Planning (General Permitted Development) Order 1995 sets out details for developments that might be permitted without requiring a planning application.
There are three main types of planning permission:
- Outline
- Reserved matters
- Full planning (or detailed planning) permission.
[edit] Outline
Outline planning permission is an application for undertaking a development in principle. The applicant can use it to find out whether their proposed development is likely to be approved by the planning authority before substantial costs are incurred developing a detailed design. Outline planning applications allow the submission of outline proposals, the details of which may be agreed as 'reserved matters' applications at a later stage (see below).
For more information see: Outline planning application
[edit] Reserved matters
Once outline planning consent has been obtained, the reserved matters stage is the follow-up which gives the applicant the opportunity to provide (usually within three years) more detail, including:
- The layout of buildings within the proposed development.
- The precise height, width and length of individual buildings.
- The appearance of buildings.
- Access to and within the site for vehicles, cycles and pedestrians.
- Landscape proposals.
The details of the reserved matters application must be in line with the outline approval, including any conditions attached to the permission. It may be necessary to reapply for outline or full planning permission if the proposals have changed significantly.
For more information see: Reserved matters.
[edit] Full planning (or detailed planning) permission
Where alteration or erection of buildings (or a change of use) is required, full planning permission is the most widely used option. It is made for developments that include building, engineering or other works, in, on, over or under land, or the making of any material change in the use of any buildings or other land.
A full planning application is made in detail, in one go – with no preliminary or outline stages – and consent, if granted, is for a limited time period. If the development does not begin within this period, the applicant must apply for a renewal of limited permission.
For more information see: Detailed planning application.
[edit] Others
Other types of planning consent that might be required include:
- Listed building consent
- Advertisement consent
- Lawful Development Certificate
- Prior approvals
- Removal/variation of conditions
- Discharge of conditions
- Consent under Tree Preservation Orders
- Notification of proposed works to trees in conservation areas
- Application for non-material amendments
[edit] Related articles on Designing Buildings Wiki
- Approved documents.
- Approved inspector.
- Building codes.
- Building control body.
- Building control performance standards.
- Building notice.
- Building Regulations Advisory Committee (BRAC).
- Building regulations completion certificate.
- Building regulations inspection.
- Building warrant (Scotland).
- Do the building regulations apply to existing buildings?
- Failure to comply with the building regulations.
- Full plans.
- How long it takes to get building regulations approval and how long it lasts.
- Independent review of the building regulations and fire safety.
- Planning permission.
- Scottish building standards.
- Standard Assessment Procedure.
- Statutory approvals.
- Statutory authorities.
- The Building Act.
- The difference between planning permission building regulations approval.
- Welsh building regulations.
- What approvals are needed before construction begins.
Featured articles and news
Designing for neurodiversity: driving change for the better
Accessible inclusive design translated into reality.
RIBA detailed response to Grenfell Inquiry Phase 2 report
Briefing notes following its initial 4 September response.
Approved Document B: Fire Safety from March
Current and future changes with historical documentation.
A New Year, a new look for BSRIA
As phase 1 of the BSRIA Living Laboratory is completed.
A must-attend event for the architecture industry.
Caroline Gumble to step down as CIOB CEO in 2025
After transformative tenure take on a leadership role within the engineering sector.
RIDDOR and the provisional statistics for 2023 / 2024
Work related deaths; over 50 percent from constructuon and 50 percent recorded as fall from height.
Solar PV company fined for health and safety failure
Work at height not properly planned and failure to take suitable steps to prevent a fall.
The term value when assessing the viability of developments
Consultation on the compulsory purchase process, compensation reforms and potential removal of hope value.
Trees are part of the history of how places have developed.
The increasing costs of repair and remediation
Highlighted by regulator of social housing, as acceleration plan continues.
Free topic guide on mould in buildings
The new TG 26/2024 published by BSRIA.
Greater control for LAs over private rental selective licensing
A brief explanation of changes with the NRLA response.
Practice costs for architectural technologists
Salary standards and working out what you’re worth.
The Health and Safety Executive at 50
And over 200 years of Operational Safety and Health.
Thermal imaging surveys a brief intro
Thermal Imaging of Buildings; a pocket guide BG 72/2017.